18-stage smart sensor factory layout & AGV replenishment lanes
02 18-stage smart sensor factory layout & AGV replenishment lanes
CR-8000 / CR-287 automated resistance welding array
03 CR-8000 / CR-287 automated resistance welding array
Inline deep-learning post-weld AOI inspection cell
04 Inline deep-learning post-weld AOI inspection cell
4-bay EOL thermal bath resistance & Hi-Pot testing line
05 4-bay EOL thermal bath resistance & Hi-Pot testing line

Station architecture and quality gates

4 connected process stages engineered for repeatable cycle time and inline verification.

  1. STAGE 1–6 Multi-Cell Parallel

    Front Array: CR-8000 Welders (×4) + CR-8700 AOI + CR-8901

    Quality gate: Logs real-time weld V/I/pressure + flags spatter & flying-wire shorts

  2. STAGE 7–12 Unmanned Continuous

    Mid Bay: 4× CR-9363A 6-Axis Robots + CR-8100D + CR-9368A

    Quality gate: Continuous multi-zone oven curve telemetry + potting weight alarms

  3. STAGE 13–16 100% Inline Sort

    Rear Bay: CR-8226 Thermal R-T & Dual Hi-Pot + Laser Mark

    Quality gate: Automatic zero-mixup NG ejection + raw-material-to-serial genealogy

  4. STAGE 17–18 24/7 Lights-Out

    AGV Carrier Loops, Auto Packaging & Open MES / SCADA Layer

    Quality gate: Native Siemens S7-1500/1200, Mitsubishi MC, Omron Fins & Modbus

Before vs. after workshop economics (4 metrics)
Operational impact comparison for PRJ-MES-03: 18-Stage Lights-Out NTC Sensor Smart Factory with Robots & MES
MetricManual baselineAutomated lineOperational impact
Workshop Supervision 20+ operators across disconnected machine islands1–2 line supervisors + AGV rack replenishmentLights-out shift capability
Weld Parameter Control Manual periodic pull test only100% per-cycle V/I/pressure waveform & AOI photo archiveStops batch drift immediately
ERP / MES Integration Manual shift spreadsheets & paper travelersReal-time SCADA OEE, digital FAI & ERP/WMS API syncPaperless multi-PLC factory
Material Logistics Manual trolley pushing between 18 stepsCR-8901 smart conveyors + 4× 6-axis robots + AGVsCuts WIP queue by >60%
Footprint, utilities and technical parameters (6 specs)
Verified mechanical, electrical, and tooling specifications for PRJ-MES-03
Engineering parameterVerified specification
Core Equipment Suite CR-8000 Welders (×4), CR-8700 AOI, CR-8901 Conveyors, CR-9363A Robots (×4), CR-8100D Potting, CR-9368A Ovens, CR-8226 Tester
Process Coverage Full 18-stage official NTC blueprint: Element Sort → Weld → AOI → Coat → Cure → Pot → Dual Hi-Pot → Mark → Pack
Telemetry & Data Archive Weld voltage/current/pressure, AOI defect images, resin batch & dose weight, oven temp zones, Hi-Pot breakdown V/I
Native PLC Connectivity Siemens S7-1500/1200/400/300, Mitsubishi A-1E/MC, Omron Fins, Modbus TCP/RTU
Enterprise Software API Open plugin interface connecting upstream ERP, WMS, QMS & live SCADA Andon boards
Intralogistics Automated AGV docking stations linking Front, Mid, and Rear workshop zones
Detailed station notes, root bottlenecks and Shenzhen FAT criteria

Root bottlenecks solved

  • Unmonitored weld voltage/pressure drift generated hidden batch defects discovered hours later.
  • Manual rack hauling between welding, coating, curing ovens, and testing created high WIP and floor congestion.
  • Mixed-brand factory PLCs (Siemens, Mitsubishi, Omron) prevented unified OEE and alarm visibility.

Shenzhen FAT acceptance gates

  • Live SCADA Andon dashboard verified collecting real-time weld V/I/force and oven temperatures across mixed PLC protocols.
  • Automated NG slot tracking proven across CR-8700 AOI through CR-8226 electrical tester with zero defective escape.
  • 6-axis robot transfer repeatability and AGV rack docking validated across continuous multi-hour endurance runs.
  • Open ERP/MES plugin API stress-tested for full lot-to-serial genealogy query under 2 seconds.

Full station engineering breakdown

STAGE 1–6

Front Array: CR-8000 Welders (×4) + CR-8700 AOI + CR-8901

Automates thermistor sorting, forming, wire alignment, and 4-cell resistance welding linked by CR-8901 smart conveyors straight into CR-8700 post-weld CCD inspection.

STAGE 7–12

Mid Bay: 4× CR-9363A 6-Axis Robots + CR-8100D + CR-9368A

Four 6-axis robots tend primary waterproof coating, CR-9368A tunnel curing, secondary encapsulation, shell insertion, and CR-8100D epoxy potting with automatic resin lot/weight capture.

STAGE 13–16

Rear Bay: CR-8226 Thermal R-T & Dual Hi-Pot + Laser Mark

Constant-temperature resistance band checking, dual dielectric withstand testing with breakdown V/I archival, automated NG ejection via CR-9365A unloader, and serial laser marking.

STAGE 17–18

AGV Carrier Loops, Auto Packaging & Open MES / SCADA Layer

AGVs replenish empty/loaded carrier racks across all 3 bays while open plugin drivers stream OEE, alarm escalations, and digital first-article inspection to factory ERP/WMS.

Direct OEM engineering desk in Shenzhen and Kunshan