Factory Acceptance Test (FAT) & CE/UL Checklist for Sourcing Sensor Automation
Lower capital cost means nothing if a custom machine jams on your raw wire or fails local electrical inspection. Use this 6-gate FAT and compliance checklist before signing any PO.
Key engineering takeaways
- Always run a witnessed Factory Acceptance Test (FAT) in Shenzhen using your actual production wires, thermistors, and housings—never generic supplier samples.
- Lock target factory voltage (480V/60Hz UL for Mexico/US vs. 400V/50Hz CE for EU/Turkey) and globally stocked BOM brands into the User Requirement Specification (URS) before machining starts.
- Pack a curated 1–2 year wear-parts kit (custom grippers, stripping blades, weld electrodes, dispensing needles) inside the main export crate to avoid customs delays later.
1. FAT vs. SAT Testing: Eliminating Sample-to-Production Surprises
The single biggest risk in custom sensor machinery is tolerance drift between lab prototypes and real-world materials—variation in PTFE jacket slickness, glass bead diameter, epoxy viscosity, or brass housing burrs. A structured Factory Acceptance Test (FAT) validates mechanical, optical, and electrical performance at our Shenzhen plant before crating, while Site Acceptance Testing (SAT) verifies identical throughput and yield after installation on your own plant floor.
Overseas buyers in Mexico, Germany, Eastern Europe, Turkey, and India can witness Shenzhen FAT in person, appoint third-party inspectors (SGS/TÜV), or verify multi-hour continuous runs via multi-camera HD live streams.
2. Pre-Shipment FAT Sign-Off Checklist (What Must Be Proven)
Never release final pre-shipment payment based on a 30-second video clip. Require documented sign-off across five quantitative FAT criteria:
- Sustained Cycle Time & UPH: Continuous dry + real-material endurance run proving rated hourly throughput (e.g., 2,000–3,000 PCS/H) without recurring feeder jams.
- Yield & False-Reject Limits: On AOI/CCD stations, verify defect escape rate (<0.1%) and false-reject rate (≤3% at ≥96% incoming yield) using a mixed batch of known good and known NG customer probes.
- Changeover Repeatability: Time a live recipe and tooling nest swap between two sensor SKUs to confirm changeover stays within the 5–15 minute target.
- Safety & Grid Compliance: Test emergency stops, door interlocks, yellow safety light curtains, and cabinet wiring against 480V/60Hz UL508A (Americas) or 400V/50Hz CE Machinery Directive (Europe/Turkey).
- Full English Documentation Pack: Verify English HMI screens, electrical/pneumatic schematics, spare parts BOM with international part numbers, and PLC/HMI backup handover before crating.
3. Protecting Local Maintenance with Global-Brand BOMs & 24h VPN Support
Domestic equipment built with obscure local sensors and locked PLCs creates painful downtime overseas. Every export proposal lets your plant specify off-the-shelf global components—Siemens, Mitsubishi, or Omron PLCs; Keyence or Cognex vision cameras; SMC or Festo pneumatics; THK/HIWIN guides; and GW Instek, Chroma, or Hioki test instruments—so local distributors stock every critical replacement.
After sea or air freight arrival, secure industrial VPN gateways allow our Shenzhen electrical and vision engineers to diagnose PLC ladder logic, alarm histories, and camera thresholds remotely within 24 business hours, backed by scheduled on-site engineer dispatch for full turnkey lines.
| Verification Gate | Factory Acceptance Test (FAT — Shenzhen) | Site Acceptance Test (SAT — Buyer Plant) |
|---|---|---|
| Materials Used | Shipped buyer wires, beads, shells & resin | Full local production lots & factory utilities |
| Throughput Proof | Multi-hour continuous UPH & OEE benchmark | Full 8-hour shift target verification |
| Quality & MSA | Gage R&R, Hi-Pot calibration & AOI sample test | Production first-article & IATF audit sign-off |
| Electrical & Safety | Target voltage panel (480V UL / 400V CE) check | Plant grid tie-in, grounding & EHS sign-off |
| Training & Spares | English manuals + 2-yr wear-parts crate check | Hands-on operator & maintenance team training |
Engineering Q&A
How many customer sensor samples are needed for Shenzhen FAT?
How much faster and more cost-effective is Shenzhen OEM delivery vs. European integrators?
More engineering guides
All 7 guidesVacuum Potting Process: Eliminating Voids in Automotive NTC Sensor Epoxy
AI Visual Inspection & ±20 μm AOI for Glass & Welded NTC Sensors
NTC vs. RTD Temperature Sensor Manufacturing: Process & Automation Guide